THIRD LEVEL AND SECOND LEVEL (EAST WING)  WILL REOPEN ON THURSDAY, MAY 17

  • Striping is now being completed including painting the curbs yellow.

The objective of the River/Front Parking Garage Restoration Project is to extend the serviceable life of the parking structure by performing various repairs throughout, including concrete repairs, expansion joint replacements, epoxy injections, drainage installations, installation of a new traffic topping for the upper deck and ramps, barrier and rail improvements, and other architectural repairs.

Fiscal impact: The project is fully funded in the Downtown Parking Fund CIP FY2017 budget under project River/Front and Cedar Garages Deck Restoration (c401508) with a construction cost estimate of $1,100,000. There is no impact to the General Fund.

Project Manager: Nathan Nguyen, (831) 420-5188, nnguyen@cityofsantacruz.com

Contractor: Pullman SST, Inc.